UK engineering. Global perspective.+44 (0) 1892 664250
Back to case studies

Full case study

LDPE & LLDPE Pellets - Jumbo Bag filling

Multinational Indian conglomerate Reliance have a strong presence in a number of industries, including petrochemicals and telecommunications. Reliance’s Jamnagar Petroleum Refinery is the largest in the world.

LDPE & LLDPE Pellets - Jumbo Bag filling
Project referenceIndia
Project referenceLDPE and LLDPE Pellets
Project referenceBulk Bags - up to 1100kg
Project reference45 x 1.1 Ton Bag Per Hour

Client

Multinational Indian conglomerate Reliance have a strong presence in a number of industries, including petrochemicals and telecommunications. Reliance’s Jamnagar Petroleum Refinery is the largest in the world.

www.ril.com

Webster Griffin recently supplied a package of three Big Bag Filling lines for processing LDPE and LLDPE Resin and Pellets to Jamnagar.

Challenge

  • The characteristics of the product meant the third system was required to be ATEX compliant across the board
  • This system was also earmarked to be connected to several different product feed points
  • Contaminated product not acceptable
  • All three units had to be integrated with the customers existing control systems
  • Machines had to connect at height to customer’s substantial system of product distribution silos
  • The machines were supplied with two storey self-supporting platforms to allow operator access to the systems dosing valves and feed system
  • The customer had a rigorous quality assurance system involving two third party consultants
  • Systems were to be fitted with dust extraction units to mitigate risks of product dust
  • Both Weighing and Check Weighing of filled bags. Refilling of underweight bags
  • The customer wanted to be able to see Bag and Weight data for analysis and identification
  • The customer wanted to be able to run the plant with minimal labour

Solution

  • Webster Griffin proposed variations on the robust IBC PF4 machines modified through discussions with the customer and project consultants to suit the product to be processed by each machine
  • Inline metal detection fitted to system feeds
    Buffer hoppers and dosing valves for control of product moving from the main silos
  • 2 x Weigh platforms for bag weighing and check weighing
  • Vibration table for maximum compaction of product
  • Inline ticket printing system accessible to the operator for application of tickets
  • Bag data transmission and logging
  • Central operator platform enabled application of bag labels and bag tying from one point.
  • Third system was designed to move along a WG supplied rail to allow connection to one of three silos

Result

  • The system achieved 45 Jumbo Bags/hour throughput
  • Excellent weight accuracy
  • Reliable system running 24 hours
  • Reduction in labour requirements to two machine operators and 1 forklift operator

Other Industry Experience

Published videos

Supporting documents

Published case study PDFPublished archive document · PDF

Bring the discussion to your application.

Describe your product, packaging, target output and site requirements. Our team can help you define the equipment and project scope.

Build your project brief Back to the summary